In August a Tel Aviv judge let two families walk away from a stalled TAMA 38 project and cash their Sale Law guarantees. In October the Supreme Court said a lender that takes over and finishes a failed project may owe buyers compensation for the delay. Here is what each ruling says, what it does not say, and what buyers can check.
Buying a new apartment in Israel “on paper” means paying a large part of the price long before you get the keys. The law protects that money. But what happens when the developer runs out of money halfway through the build? Two court decisions from 2026 give a clearer, if still incomplete, answer.
The protection buyers already have
Under section 2 of the Sale (Apartments) (Assurance of Investments of Persons Acquiring Apartments) Law, 5735-1974, a developer may not take more than 7% of the price unless it secures the buyer’s money. The most common way is a bank or insurance guarantee, known as a “Sale Law guarantee.”
The guarantee returns the money paid toward the price (under the current text, not the VAT part). It is triggered if the developer cannot transfer the apartment because of an attachment, an insolvency order, a liquidation order, the appointment of a receiver, or an “absolute impediment” to handing over the apartment. The same section adds that cancelling the contract is not, on its own, an absolute impediment.
Separately, section 5A of the Sale (Apartments) Law, 5733-1973 gives buyers fixed compensation for late delivery, without having to prove damage. For contracts signed from 7 July 2022, it starts one month after the contract date. It equals the rent of a similar apartment, rising to 1.25 times that rent from the fifth month and 1.5 times from the eleventh. Older contracts follow the previous formula.
The old rule: guarantees are for the apartment, not for the delay
For two decades, courts read the guarantee narrowly. In CA 8343/01 Ovadia v. Sibal Nahariya (24 June 2004), the Supreme Court held that the guarantee protects the buyer’s ability to receive ownership of the apartment, not every promise the developer made. Lower courts drew from it three conditions for cashing a guarantee: the developer cannot transfer the apartment, one of the events listed in section 2(1) has happened, and the first is caused by the second.
In practice, this meant that when a lender stepped in and kept building, buyers were usually told to wait, even if delivery slipped by years.
August 2026: a judge lets two families leave
The project is a TAMA 38/1 building at 50-52 Shlonsky Street in Neot Afeka, Tel Aviv. The developer, Y. Hoiberger Yazmot Ltd., had the right to build 20 new apartments, of which 14 were sold. After it ran into trouble, Tel Aviv District Court Judge Noa Grossman appointed a receiver on 4 May 2026 at the request of the financiers, Miklal Mimun Nadlan and Clal Insurance, Globes reported.
Two families, who bought three of the new apartments, asked to cancel and cash their guarantees. The financiers objected. They told the court the building was 61% complete and should be finished in September 2027, or November 2027 “with grace.”
In her decision of 23 August 2026 (Insolvency Case 46530-04-26), Judge Grossman ruled for the families. She wrote that when the developer collapses and the financiers bring in a receiver, “this is a crisis point” at which a buyer who wishes to may cash the guarantee and leave. She found that a delay to November 2027 was significant and amounted to a fundamental breach. The six other buyers who wanted to stay could do so.
Two points matter for anyone hoping to rely on this. It is a first-instance decision in one case, not a binding precedent. And a similar 2025 District Court ruling against Bank Jerusalem was later cancelled as part of a settlement on appeal, without any ruling on the issue, as Judge Grossman herself noted. No appeal in the Shlonsky case had been reported publicly at the time of writing.

October 2026: the Supreme Court on delay compensation
The second case concerns a TAMA 38/1 project at 63 HaNevi’im Street, Bat Yam. The developer failed and a receiver was appointed in January 2021 at the request of the financiers, Yesodot A Nadlan and Ayalon Insurance. The receiver chose to finish the building but refused to pay one family compensation for late delivery.
In CA 3301/23 Midili v. Project Ibui Binui – HaNevi’im 63 Bat Yam Ltd., decided on 7 October 2026, Justice Ruth Ronen, joined by Deputy President Noam Solberg and Justice Yael Willner, allowed the family’s appeal. Globes reported the ruling on 15 October.
The court split the delay into two periods:
- Before the receiver was appointed. Compensation for this period is an ordinary old debt of the developer. It is paid only after the lender has been repaid.
- After the receiver was appointed. If the lender chooses to keep the sale contracts and finish the building, compensation for this period counts as a cost of the procedure. It ranks ahead of the lender’s general (floating) charge.
Justice Ronen wrote that a lender cannot adopt only the parts of the contract it likes. The court also said the buyers may deduct the post-appointment compensation from the balance they still owe. The case went back to the District Court to calculate the amount. The court added that lenders and buyers remain free to negotiate other terms.
The financiers have asked for a further hearing before an expanded panel, according to Magdilim. Until a decision on that, the ruling stands.
A related step: freezing money to secure compensation
In a third case, reported by Calcalist on 1 February 2026, the Tel Aviv Magistrates’ Court kept a temporary attachment of about NIS 2 million on buyers’ remaining payments in a TAMA 38/2 project at 15 Atarot Street, Ramat Gan. The money goes to the court rather than to the developer, to secure possible delay compensation. The court has not yet decided whether compensation is due.
What buyers can check
- Your guarantee. Make sure you received a Sale Law guarantee (or other legal security) for every payment above 7% of the price, and keep the originals.
- The delivery date. Note the exact contract delivery date and any grace period. Compensation is counted from there.
- The project’s status. If you hear of a receiver, find out the court and case number. Buyers can ask to be heard in that procedure.
- Your choice. Decide early, with a lawyer, whether you want the apartment late or your money back. Courts look at how long the delay is and how it affects you.
- Delay compensation. If a lender finishes the project, ask in writing how it will pay compensation for the period after the receiver was appointed, and whether you can set it off against your next payment.
- Do not sign waivers in a hurry. A lender may offer to finish the building in exchange for giving up compensation. Get legal advice first.
This article is general information, not legal advice. Every contract and case is different; speak to a real-estate lawyer about your own situation.
References
- Sale (Apartments) (Assurance of Investments of Persons Acquiring Apartments) Law, 5735-1974, s. 2 — Hebrew text (Wikisource, Open Law Book); s. 2 with amendment history (Knesset Tracker)
- Sale (Apartments) Law, 5733-1973, s. 5A — added by Amendment No. 5, 5771-2011; revised by Amendment No. 9, 5782-2022 (for contracts from 7 July 2022) — Hebrew text (Wikisource); s. 5A, both versions; Amendment No. 9, Reshumot (Knesset)
- Tel Aviv-Jaffa District Court, Insolvency Case (Pr”k) 46530-04-26, Miklal Mimun Nadlan Ltd. et al. v. Y. Hoiberger Yazmot Ltd. et al., decision of 23 August 2026, Judge Noa Grossman — full text (PDF)
- Supreme Court, Civil Appeal 3301/23, Midili v. Project Ibui Binui – HaNevi’im 63 Bat Yam Ltd. et al., judgment of 7 October 2026, Deputy President N. Solberg, Justices Y. Willner and R. Ronen; appeal from Tel Aviv District Court Pr”k 44205-01-21 (Judge I. Lushi-Abudi, 22 February 2023) — full text (PDF)
- Supreme Court, Civil Appeal 8343/01, Ovadia v. Sibal Nahariya Ltd. (in receivership), PD 58(6) 400, judgment of 24 June 2004 — Psikan
- Supreme Court, Civil Appeal 2457/24, Rachamim v. Adv. Alona Baumgarten, trustee, 14 October 2024 (cited in both 2026 decisions)
- Tel Aviv District Court, Pr”k 30215-07-24, Bank Jerusalem v. Granit, 27 July 2025; vacated by settlement on appeal, CA 13991-08-25, 3 December 2025 (as described in reference 3)
- Globes, Arik Mirovsky, 25 August 2026 — Neot Afeka ruling
- Globes, Arik Mirovsky, 15 October 2026 — Supreme Court Bat Yam ruling
- Calcalist, 1 February 2026 — Ramat Gan attachment (case number not published)
- Magdilim, 25 October 2026 — request for a further hearing in CA 3301/23